Heatmap: Federal court rejects Trump’s emergency order to keep Michigan coal plant open
In 2025, Trump ordered a Michigan coal-fired station to stay open past its planned retirement date on the grounds that the broader grid system is under an “emergency” level of stress. Maintaining the J.H. Campbell coal station for just three months past its previously-agreed closure cost the utility Consumers Energy nearly $30 million. On Sept 11, the D.C. Circuit Court of Appeals ruled against the Trump administration’s use of emergency powers to force the plant to stay open. The court found that the Department of Energy illegally invoked Section 202(c), the emergency authority of the Federal Power Act, to override the long-term planning process through which Consumers, Michigan, and the Energy Department had agreed to terminate power production at the 1.4-gigawatt plant.